Project scope
Retaining wall (January–July), drilling foundation shafts (March–June), diaphragm construction (July–August) and concrete topping slabs (August–October).Querétaro, Qro. · 2023
Work packages
- Retaining wallsJanuary–July 2023
- Foundation shaftsMarch–June 2023
- DiaphragmsJuly–August 2023
- Concrete topping slabsAugust–October 2023