Distribuidor Vial Paseo 5 de Febrero

Distribuidor Vial Paseo 5 de Febrero

Project scope

Retaining wall (January–July), drilling foundation shafts (March–June), diaphragm construction (July–August) and concrete topping slabs (August–October).Querétaro, Qro. · 2023

Work packages

  • Retaining wallsJanuary–July 2023
  • Foundation shaftsMarch–June 2023
  • DiaphragmsJuly–August 2023
  • Concrete topping slabsAugust–October 2023